Thursday, May 13, 2010
Thursday 13th May
Big bank holiday in France today (Ascension Day). No one working but a lot of progress seems to have been made. All lintels are now cast and the block work is nearly finished. Roof has been delivered!! Looks like the builder wants to get the bungalow finished and move on great!!
Saturday, May 8, 2010
Week ending 08/05/2010
Well the build is moving on, very slow. It's a big disappointment that it is taking so long to complete the block work. The roof is supposed to start next week, but there is no chance. I think it will be at least another week to ten days before the roof can start. Yes one of the pictures shows snow! 5th May it snowed and was -1, can you believe it!! Hope to have some better news next week, but don't hold out much hope.